 1. Open the inlet grille, and remove the side cover fixing screw
(right and left) from the internal part of the unit.
 2. Move the side cover to about 15mm forward to remove it.
Use the packing material (Styrene foam) to support, when
you reverse the top and bottom of the indoor unit.
 3. Remove the hanging bracket
 a. Remove the slip prevention screws of the brackets (right
and left).
 b. Loosen the hanging bracket fastening bolts to about
10mm, and remove the hanging bracket.
 • Make sure the ventilation fan for smoke-collection hood on a cooking table has sufficient capacity so that it draws oily steam
which should not flow into the suction of the air conditioner.
 • Make enough distance from cooking room to install the air conditioner in such place where it may not suck in oily steam.
 2. Avoid installing the air conditioner in such circumstances where cutting oil mist or iron powder exist especially in factories, etc.
 3. Avoid places where inflammable gas can be generated, flows-in, contaminated, or leak.
 4. Avoid places where sulphurous acid gas or corrosive gas can be generated.
 5. Avoid places near high frequency generators.
10.4.3. Installation of indoor unit
The paper template for installation may expand or shrink according to temperature and humidity. Check the dimensions before using it.
CEILING OPENING DIMENSIONS AND HANGING BOLT LOCATION
Caution
During the installation, care must be taken not to damage the electric wires.
REMOVING THE SIDE COVER AND HANGING BRACKET
33
CS-F18DTE5 CU-L34DBE5 /
* Use either W3/8 or M10 bolts and nuts (local supplied)
 • Fastening the hanging bracket
Warning
Be sure to tighten the nut and bolt to prevent the
unit from falling.
Fastening the hanging bracket
Piping hole positions
 • The refrigerant piping can be installed on the right, right upper or right rear.
 • The drain piping can be installed on the right, right rear, left or left rear (there are connection ports on both right and left sides.)
 • Thermally insulate the drain and refrigerant piping to prevent dew condensation.
 • After cutting the piping holes, use the edge protection cover (accessory) to protect the end surfaces.
Installing the unit
 1. Insert the hanging bracket fastening bolts and both sides of the unit into the hanging brackets, and slide the unit to the rear.
Fasten the bolts.
 2. Tighten the slip prevention screws (M5) for brackets to prevent the unit from shifting.
 3. To ensure correct drainage, after hanging the unit, use a level gauge to check the installation angle.
34
CS-F18DTE5 CU-L34DBE5 /
Flare nut fastening torque N.m (kgf.cm)
ø6.35 mm
18 (180)
ø15.88 mm
65 (660)
ø9.52 mm
42 (430)
ø19.05 mm
100 (1020)
ø12.7 mm
55 (560)
 • Be sure to use the drain hose provided (accessory item.)
 • Drain piping must have down-slope (1/50 to 1/100): be sure
not to provide up-and-down slope to prevent reversal flow.
 • During drain piping connection, be careful not to exert extra
force on the drain port at the indoor unit.
 • The outside diameter of the drain connection at the indoor
unit is 20 mm.
Piping material: Polyvinyl chloride pipe VP-20 and pipe fittings
Heat insulation material: Polyethylene foam with thickness more
than 8mm (local supply).
Liquid side piping
Gas side piping
ø9.52 mm
ø15.88 mm
10.4.4. Refrigerant piping
Refrigerant is charged to the outdoor unit. For details, see the manual for installation work of outdoor unit.(Additional charging,
etc.)
 1. Brazing for piping.
 a. Execute brazing before tightening the flare nut.
 b. Brazing must be executed while blowing nitrogen gas.
(This prevents generation of oxidized scale in copper pipe.)
 2. When there is a lot of brazing for long piping, install a strainer at the midway of the piping.
(The strainer is locally supplied.)
 3. Use clean copper pipe with inner wall surface free from mist and dust. Blow nitrogen gas or air to blow off dust in the pipe before
connection.
 4. Form the piping according to its routing. Avoid bending and bending back the same piping point more than three times.
(This will result in hardening of the pipe).
 5. After deforming the pipe, align centers of the union fitting of the indoor unit and the piping and tighten them firmly with wrenches.
 6. Connect pipe to the service valve or ball valve which is located below the outdoor unit.
 7. After completed the piping connection, be sure to check if there is gas leakage in indoor and outdoor connection.
 • Confirm the red mark of the union (thin side) is always at lower direction after connecting piping.
Vacuum drying
After completing the piping connection, execute vacuum drying for the connecting piping and the indoor unit.
The vacuum drying must be carried out by using the service ports of both the liquid and gas side valves.
CAUTION Use two wrenches and tighten with regular torque.
10.4.5. Indoor unit drain piping
35
CS-F18DTE5 CU-L34DBE5 /
Be sure to perform heat insulation on the drain piping.
Caution
If insulation is insufficient, dew may form.
This causes water leakage.
Prevent the drain hose from floating and hanging
Caution
down.
This causes water leakage. (down figure)
Wall seal
 • When the outdoor unit is installed on a higher position
than the indoor unit, install the trap so as not to instill
rain water into the wall by transmitted in piping.
 • Stuff the space among piping, the electric wire, and the
drain hose with “Putty” and seal the penetration wall
hole.
Make sure that rain water do not instill into the wall.
In the case of left piping
 1. Remove both the internal and external plugs.
 2. Use a wrench or pliers to remove the plugs.
 • Putting substitution of rubber plug.
Drain Test
Confirm the drain water flows smoothly after connecting the
drain piping.
 • Pour water to about 1.5 litres for the drain confirmation from
the air inlet part which should gradually flow into the drain
pan.
10.4.6. Heat insulation
Caution
Be sure to perform heat insulation on the drain, liquid and gas piping. Imperfection in heat insulation work leads to water
leakage.
 1. Use the heat insulation material for the refrigerant piping which has an excellent heat-resistance (over 100°C).
 2. Precautions in high humidity circumstance.
This air conditioner has been tested according to the “JIS Standard Conditions with Mist” and have been confirmed that there
is no form of any faults. However, if it is operated for a long time in high humid atmosphere (dew point temperature: more than
23°C), water drops are liable to fall.
 • In addition to the normal heat insulation (thickness: more than 8 mm) for refrigerant piping (gas piping: thick piping) and
drain piping, add a further of 10 mm to 30 mm thickness material.