JBL VOYAGER (serv.man2) EMC - CB Certificate ▷ View online
Report No.: EM201300534-2 Application No.: ZJ00032799 Page 49 of 58
5.8.4 TEST RESULTS
EUT
Wireless speaker system
Mode Number
JBL VOYAGER
Test date
2013-08-08
Voltage Supply
AC 230V/50HZ
Test Engineer
Bruce
environment
Tem:20℃ Hum:54 %101kPa
Test mode:
1. Test the EUT in mode 1:
AUDIOIN
(adapter)
2. Test the EUT in mode 2:
BT
(adapter)
3. Test the EUT in mode 3:
BT
(battery)
4. Test the EUT in mode 4: Standby
Voltage
(% Reduction)
Duration
(Period)
Angle
Required
Passing
Performance
Actual
performance
Test
Result
Voltage
dips
100% 0.5
0°
Criterion B
A*
PASS
180°
Voltage
dips
100% 1
0°
Criterion B
A*
PASS
180°
Voltage
dips
30% 25
0°
Criterion B
A*
PASS
180°
Voltage
interruptions
100% 250
0°
Criterion C
A*
PASS
180°
Note: A*: EUT is working on intended use operation, no abnormal phenomenon was observed.
B*: There was the EUT shut up and restore to the original working state automatically.
C*: There was the EUT shut up and need restart by the operator.
C*: There was the EUT shut up and need restart by the operator.
Report No.: EM201300534-2 Application No.: ZJ00032799 Page 50 of 58
APPENDIX A: PHOTOGRAPH OF THE TEST CONFIGURATION
RE (Below 1GHz)
RE (Above 1GHz)
Report No.: EM201300534-2 Application No.: ZJ00032799 Page 51 of 58
CE
Flicker
Report No.: EM201300534-2 Application No.: ZJ00032799 Page 52 of 58
ESD
RS (Below 1GHz)